title: How to Create a Bill from a Purchase Order
description: Buildern allows you to create a Bill directly from a Purchase Order (PO), eliminating the need to manually re-enter cost information. In this article, you'll learn how to create a Bill from a Purchase Order.
---

[Skip to content](https://help.buildern.com/en/articles/13773987-how-to-create-a-bill-from-a-purchase-order#main-content)

![logo\_icon\_text](https://help.buildern.com/hubfs/Buildern%20logo.svg)

- [My Account](https://app.buildern.com/signin)

Open main navigation

Close main navigation

- [My Account](https://app.buildern.com/signin)
- [Get Started Free](https://app.buildern.com/signup)

[Get Started Free](https://app.buildern.com/signup)

 Welcome to Buildern Help Center!

- There are no suggestions because the search field is empty.

1. [Buildern Help Center](https://help.buildern.com/en/articles?hsLang=en-gb)
2. [Bills](https://help.buildern.com/en/articles/bills?hsLang=en-gb)

# How to Create a Bill from a Purchase Order

### How to Create a Bill from a Purchase Order

Buildern allows you to create a Bill directly from a Purchase Order (PO), eliminating the need to manually re-enter cost information. In this article, you'll learn how to create a Bill from a Purchase Order.

 July 14, 2026

### **📋 Requirements**

Before you begin, make sure:

- You have access to Buildern.
- You have permission to create Bills.
- A Purchase Order has already been created.

### **Create a Bill from a Purchase Order**

To create a Bill from a Purchase Order:

1. Navigate to the relevant **Project** or go to **All Items → POs & Subcontracts**.
2. Locate the Purchase Order you want to bill against.
3. Click the **three-dot menu (⋮)** at the end of the Purchase Order row.
4. Select **Create → Bill**. The **Bill Edit** page will open.

[![](https://help.buildern.com/hubfs/Knowledge%20Base%20Import/e51d26d3-83d0-4805-a221-2348ed6835f6.png)](https://downloads.intercomcdn.com/i/o/suco1tn6/2514612994/c1b2c5291950301c18dfd76ede00/e51d26d3-83d0-4805-a221-2348ed6835f6?expires=1792671300&signature=523b08665b5c6d1fb2a17e79bef19ae709ea542b69d4acf68bcaec70675f3565&req=diUmEs9%2Fn4hWXfMW1HO4zSvoeh2cJr825wDMRxOUiDk9AmTKukhZeTYzkRjh%0ARCC2SclOd%2Bp%2BCEgDV%2F8%3D%0A)[![](https://help.buildern.com/hubfs/Knowledge%20Base%20Import/f4bda573-8e25-4b85-b7fe-ff12cdbccd98.png)](https://downloads.intercomcdn.com/i/o/suco1tn6/2514612991/e2567d4806f203cfb087612e5ae6/f4bda573-8e25-4b85-b7fe-ff12cdbccd98?expires=1792671300&signature=3f60ba27255dc4c98db1e73302e67fe763409690310431cdd350bf60ab4bf812&req=diUmEs9%2Fn4hWWPMW1HO4zXenMgXNY3h3CSAmMq4vXt248OXj8hX8lAd8niLS%0ASxCbq%2BjVEqMGUY20VpQ%3D%0A)

### **Review and Complete the Bill**

When creating a Bill from a Purchase Order, Buildern automatically fills in several fields, including:

- Bill Name
- Bill ID
- Related Purchase Order

[![](https://help.buildern.com/hubfs/Knowledge%20Base%20Import/b0d2a56c-0c93-4b51-a171-44e3cd7c13da.png)](https://downloads.intercomcdn.com/i/o/suco1tn6/2514612996/d4480d46684d4edf69ff2416ebd5/b0d2a56c-0c93-4b51-a171-44e3cd7c13da?expires=1792671300&signature=171d6162e93b187cc7e670192393e64bb714c96228f1c0721842745103b80640&req=diUmEs9%2Fn4hWX%2FMW1HO4zTNAi2iEHBLtPYnDbdU0sC5mTzfUnYhiOKz23BvO%0AweLvuUFSATwKwf56NL0%3D%0A)

You can Complete or update any additional bill information. The cost lines from the Purchase Order are automatically copied to the bill.

[![](https://help.buildern.com/hubfs/Knowledge%20Base%20Import/bb38b9ee-072a-45e5-9718-44b1ded0963e.png)](https://downloads.intercomcdn.com/i/o/suco1tn6/2514612990/2ae418ee5c05ce1b576499cf7ce7/bb38b9ee-072a-45e5-9718-44b1ded0963e?expires=1792671300&signature=2c07f16fc66f519709e9f94a81dc72a2c08bea416b3f7c4136fc3706922c7cb6&req=diUmEs9%2Fn4hWWfMW1HO4zX91GQXBAxTkmbgCam3MIcXCx9LbQC2p2ZSvm6Tb%0AXm7n7Xgz0IFpY5i0uEM%3D%0A)

***ℹ️ Note -*** *The item name from the Purchase Order is transferred to the bill as the Description.*

[![](https://help.buildern.com/hubfs/Knowledge%20Base%20Import/603fa557-8302-4ba6-9590-cd465b42732f.png)](https://downloads.intercomcdn.com/i/o/suco1tn6/2514612993/db2493fb63217a8cf57111c9b68a/603fa557-8302-4ba6-9590-cd465b42732f?expires=1792671300&signature=90f150251ec456314950d6edf9f590c3749fcd624891ad762db9381a02e923d9&req=diUmEs9%2Fn4hWWvMW1HO4zV64TLAadXooYNeuTPfFLfH%2BBViP1BCS2VW1JszY%0Av3UkBE6n9RmaHSQ%2FEu4%3D%0A)

For each cost line, you can use the **Type** field to associate the bill item with:

- an Estimate Item
- an Allowance
- a Change Order item

[![](https://help.buildern.com/hubfs/Knowledge%20Base%20Import/c8928356-9166-42e8-b70e-2bf7b6db22a7.png)](https://downloads.intercomcdn.com/i/o/suco1tn6/2514613003/32b8f7a8167c3ed3d7a6cd295ae1/c8928356-9166-42e8-b70e-2bf7b6db22a7?expires=1792671300&signature=237e5eb865a926454f0a1551405a20af499915842c319d35bee2a8d77628da93&req=diUmEs9%2FnoFfWvMW1HO4zfI1ypDH4BTEtqbvUb5N0A1%2BlePNfA8mYeqm87B7%0APQrVo8Iu2qZHr3qdIXo%3D%0A)

If Taxes are enabled for your account, choose how taxes should be applied to the bill by selecting one of the following options in the upper-right corner of the Cost Lines section:

- **Tax Inclusive**
- **Tax Exclusive**
- **No Tax**

[![](https://help.buildern.com/hubfs/Knowledge%20Base%20Import/db1a73c0-18e7-4dc8-ab40-28c59b7e6322.png)](https://downloads.intercomcdn.com/i/o/suco1tn6/2514612999/7500adce7c2b0393e21545e16ef8/db1a73c0-18e7-4dc8-ab40-28c59b7e6322?expires=1792671300&signature=7ab3bc3856469be8e0eaa596d58e9861971f3bed21221b7ab8b08c20448ee2ca&req=diUmEs9%2Fn4hWUPMW1HO4zZgZv2mq47QxRm%2BEboZs5kGp8wZTtPkh32WC7x7k%0AwlU9S97XxGE5NSJqbjg%3D%0A)

If the bill has already been paid, you can record the payment before saving the bill.

[![](https://help.buildern.com/hubfs/Knowledge%20Base%20Import/b82b38b4-2273-4fbc-aa7b-90264d5afb9e.png)](https://downloads.intercomcdn.com/i/o/suco1tn6/2514613000/a72cfb88fab0105b1c541e359eb1/b82b38b4-2273-4fbc-aa7b-90264d5afb9e?expires=1792671300&signature=5bc9a7d6425276da9472903caa169eac5f1fd173d2b9316484310a9980f1cb00&req=diUmEs9%2FnoFfWfMW1HO4zRrpuTrNEK2NaBKTb0rHJYJKWrHIguq8DbTk5D4f%0Afo7JqB81arjs%2FkjMtgw%3D%0A)[![](https://help.buildern.com/hubfs/Knowledge%20Base%20Import/76771de8-fc6a-48b6-8700-ec87a20d804e.png)](https://downloads.intercomcdn.com/i/o/suco1tn6/2514613001/7f636c2a31447dc790c84d597334/76771de8-fc6a-48b6-8700-ec87a20d804e?expires=1792671300&signature=f7950d6bddbc01bff11b1d65eb5e70fe39b02836989fc4bd6351d440d901ac99&req=diUmEs9%2FnoFfWPMW1HO4zVTRqI1nmB1Qykj1bzf6IndBNyx3LhuTTe%2Fha%2Be6%0AkNGVf55SZ86vGK527cc%3D%0A)

Once you've finished entering all the bill details, you can either click **Save** or select the arrow next to the **Save** button to access additional save options.

[![](https://help.buildern.com/hubfs/Knowledge%20Base%20Import/56431a94-a10e-4009-a0db-4b8f87eeccb3.png)](https://downloads.intercomcdn.com/i/o/suco1tn6/2539335394/55bf94bf275853e107d4c08f9c49/56431a94-a10e-4009-a0db-4b8f87eeccb3?expires=1792671300&signature=397ded4316a359a92cda06ad7495dde74b373ec26083952261ce98f5cf928cc6&req=diUkH8p9mIJWXfMW1HO4zYRE7hwMjmhT%2FYzAbVQh2QHiLAO9xFJ%2BH%2B1yFsQz%0A7dvGUK7l2BJcgsdLKwo%3D%0A)

The available options are:

- **Save and Add Another** – Saves the current bill in **Draft** status and immediately opens a new bill creation page, allowing you to continue entering additional bills.
- **Submit for Approval** – Submits the bill for internal approval and changes its status to **Awaiting Approval**, making it ready for the approval workflow.
- **Save and Approve** – Saves the bill and immediately changes its status to **Approved**.
- **Approve and Next** – Approves the current bill and automatically opens the next bill in the list for review.

[![](https://help.buildern.com/hubfs/Knowledge%20Base%20Import/bfc9f0fe-b7fc-47da-ac68-5bb87785577d.png)](https://downloads.intercomcdn.com/i/o/suco1tn6/2539335393/4330111159472e61f4ab721d5470/bfc9f0fe-b7fc-47da-ac68-5bb87785577d?expires=1792671300&signature=c5a9005eafad03030adc1bae1fa9e0c13312bb1d3e943bb2968b8cd77807ea06&req=diUkH8p9mIJWWvMW1HO4zaZ9ASPDQvwbv5YkD%2FdJGfl3rJb3IMplDGZ0Uw3r%0A2ae79RqmKB7BTetiCRg%3D%0A)

*💡 **Tip:** If you’d like to quickly review and approve multiple draft bills, navigate to the Bills page and filter the list by **Draft** and **Awaiting Approval** status. Then, open the first bill and click Approve and Next. Buildern will automatically open the next draft/awaiting approval bill, allowing you to approve your bills one by one without returning to the bills list each time. This provides a fast and efficient way to work through all of your draft bills.*

👉 Learn more about [PO, Subcontract and Bill approval workflow](https://help.buildern.com/en/articles/15857982-approval-workflows-for-purchase-orders-subcontracts-and-bills?hsLang=en-gb)

You're ready to go! Continue exploring Buildern to discover more tools that can help simplify your construction management.

Happy building!

- [Getting started](https://help.buildern.com/en/articles/getting-started?hsLang=en-gb)
- [Projects](https://help.buildern.com/en/articles/projects?hsLang=en-gb#main-content)

    - [Getting Started with Projects](https://help.buildern.com/en/articles/projects?hsLang=en-gb#getting-started-with-projects)
    - [Projects Explained](https://help.buildern.com/en/articles/projects?hsLang=en-gb#projects-explained)
- [Dashboards](https://help.buildern.com/en/articles/dashboards?hsLang=en-gb)
- [Takeoff](https://help.buildern.com/en/articles/takeoff?hsLang=en-gb)
- [Estimates](https://help.buildern.com/en/articles/estimates?hsLang=en-gb#main-content)

    - [Creating and Editing an Estimate](https://help.buildern.com/en/articles/estimates?hsLang=en-gb#creating-and-editing-an-estimate)
    - [Estimate Measurements](https://help.buildern.com/en/articles/estimates?hsLang=en-gb#estimate-measurements)
    - [Getting Started with Estimates](https://help.buildern.com/en/articles/estimates?hsLang=en-gb#getting-started-with-estimates)
    - [Importing Estimates](https://help.buildern.com/en/articles/estimates?hsLang=en-gb#importing-estimates)
- [Cost Codes](https://help.buildern.com/en/articles/cost-codes?hsLang=en-gb#main-content)

    - [Getting Started with Cost Codes](https://help.buildern.com/en/articles/cost-codes?hsLang=en-gb#getting-started-with-cost-codes)
    - [Importing Cost codes](https://help.buildern.com/en/articles/cost-codes?hsLang=en-gb#importing-cost-codes)
- [Proposals](https://help.buildern.com/en/articles/proposals?hsLang=en-gb)
- [Schedule](https://help.buildern.com/en/articles/schedule?hsLang=en-gb#main-content)

    - [Schedule Board Explained](https://help.buildern.com/en/articles/schedule?hsLang=en-gb#schedule-board-explained)
    - [Importing Schedule](https://help.buildern.com/en/articles/schedule?hsLang=en-gb#importing-schedule)
    - [Getting Started Schedule](https://help.buildern.com/en/articles/schedule?hsLang=en-gb#getting-started-schedule)
- [Bid Requests / Request for Quote](https://help.buildern.com/en/articles/bid-requests-request-for-quote?hsLang=en-gb)
- [Selections and Allowances](https://help.buildern.com/en/articles/selections-and-allowances?hsLang=en-gb)
- [Purchase Orders](https://help.buildern.com/en/articles/purchase-orders?hsLang=en-gb)
- [Bills](https://help.buildern.com/en/articles/bills?hsLang=en-gb)
- [Budget Tab](https://help.buildern.com/en/articles/budget-tab?hsLang=en-gb)
- [Change Orders / Variations](https://help.buildern.com/en/articles/change-orders-variations?hsLang=en-gb)
- [Quickbooks Online Integration](https://help.buildern.com/en/articles/quickbooks-online-integration?hsLang=en-gb)
- [Xero Integration](https://help.buildern.com/en/articles/xero-integration?hsLang=en-gb)
- [Client Invoices](https://help.buildern.com/en/articles/client-invoices?hsLang=en-gb#main-content)

    - [Client Invoices Explained](https://help.buildern.com/en/articles/client-invoices?hsLang=en-gb#client-invoices-explained)
    - [Getting Started with Invoices](https://help.buildern.com/en/articles/client-invoices?hsLang=en-gb#getting-started-with-invoices)
- [To-Dos](https://help.buildern.com/en/articles/to-dos?hsLang=en-gb)
- [Daily Logs / Site diary](https://help.buildern.com/en/articles/daily-logs-site-diary?hsLang=en-gb)
- [Timesheets](https://help.buildern.com/en/articles/timesheets?hsLang=en-gb)
- [Files](https://help.buildern.com/en/articles/files?hsLang=en-gb)
- [Users, Roles, Permissions](https://help.buildern.com/en/articles/users-roles-permissions?hsLang=en-gb)
- [Clients](https://help.buildern.com/en/articles/clients?hsLang=en-gb)
- [Subcontractors & Vendors](https://help.buildern.com/en/articles/subcontractors-vendors?hsLang=en-gb)
- [Templates](https://help.buildern.com/en/articles/templates?hsLang=en-gb)
- [Settings and Configurations](https://help.buildern.com/en/articles/settings-and-configurations?hsLang=en-gb)
- [Buildern AI](https://help.buildern.com/en/articles/buildern-ai?hsLang=en-gb)
- [General](https://help.buildern.com/en/articles/general?hsLang=en-gb)

- [My Account](https://app.buildern.com/signin)

[![logo\_icon\_text](https://help.buildern.com/hubfs/Buildern%20logo.svg "logo_icon_text")](https://buildern.com/)

<https://www.facebook.com/buildernsoft> <https://www.instagram.com/buildern.soft> <https://www.linkedin.com/company/buildern> <https://x.com/Buildern_>

Copyright © 2026, Buildern Inc.